Sri Lanka’s expressway network earned Rs. 27,581.4 million in revenue between January 2025 and 31 October 2026, Transport, Highways and Urban Development Minister Bimal Rathnayake told Parliament on Saturday.
The Southern Expressway, which runs from Kottawa to Mattala, earned the most, at Rs. 11,486 million. The Mirigama to Kurunegala section of the Central Expressway followed with Rs. 7,282 million.
The Outer Circular Expressway recorded revenue of Rs. 6,251 million over the same period, while the Colombo-Katunayake Expressway earned Rs. 2,560.05 million.
The Minister said the Southern, Central and Colombo-Katunayake expressways together earned about Rs. 21,328 million.
Rathnayake also gave completion dates for sections still under construction. The Kadawatha to Mirigama section of the Central Expressway is divided into three packages, and he said it is on schedule under the contractually agreed timelines.
- The Kadawatha interchange is due by January 2027.
- The Kadawatha to Kosinna package is due by March 2028.
- The Kosinna to Mirigama package is due by September 2028.
The Pothuhera to Galagedara section of the Central Expressway is being built in two phases. Phase 1 is scheduled for completion by 31 May 2027 and Phase 2 by 17 May 2029.
The Kurunegala to Dambulla section is also planned in two phases, with Phase 1 due by 1 June 2030. The Minister said construction of the Galewela to Dambulla section has not yet begun.
Background
The Southern Expressway was the country’s first expressway, and its first section opened in 2011. The Colombo-Katunayake Expressway followed in 2013, linking the capital with the area around Bandaranaike International Airport.
The Central Expressway is being built in sections rather than as one project. The revenue figures the Minister gave for it cover only the Mirigama to Kurunegala section, which means the other sections listed in his statement are not yet contributing to the total.
The Minister’s figures are for a period of 22 months, from the start of January 2025 to the end of October 2026, so they are not annual totals.
What it means
The figures give road users and taxpayers a picture of how much the expressway network earns while new sections are still being built.
The completion dates matter for people who travel regularly between Colombo, Kurunegala and Dambulla, as the later phases of the Central Expressway are not due until between 2027 and 2030. Work on the Galewela to Dambulla section has not started, so no completion date has been given for it.